Programación, optimización de obra del proyecto "construcción de parques en los municipios de Pitalito y la Plata en el departamento del Huila".

Fecha
2021-01-24
Autores
Osorio Esquivel, Jaime Alexander
Tovar Barrera, William Andres
Título de la revista
ISSN de la revista
Título del volumen
Editor
Universidad Cooperativa de Colombia, Facultad de Ingenierías, Ingeniería Civil, Neiva
Resumen
The main objective is to optimize the schedule in periods shorter than that established in the contract "Construction of parks in the municipalities of Pitalito and La Plata in the department of Huila", to evaluate if the reduction in the time of development and execution of the contract is feasible according to the analysis of costs assigned to the contract, using the Project software and implementing the knowledge acquired in the in-depth seminar. Exploring the use of this tool for the application in the development of the work schedule, covering estimated times, human resources, machinery, equipment and budget.
Descripción
El objetivo principal es realizar la optimización del cronograma en periodos inferiores al establecido en el contrato “Construcción de parques en los municipios de Pitalito y la Plata en el departamento del Huila”, para evaluar si la disminución del tiempo de desarrollo y ejecución del contrato es factible conforme al análisis de costos adscritos al contrato, utilizando el software Project e implementando los conocimientos adquiridos en el seminario de profundización. Explorando el uso de esta herramienta para la aplicación en el desarrollo del cronograma de obra, abarcando tiempos estimados, recurso humano, maquinaria, equipo y presupuesto.
Palabras clave
Consorcio , Contratista , Cronograma , Presupuesto , Programacion , Proyecto , Recursos